November 16, 2016 – Board of Commissioner Chairman Ellis’ report indicates a roundabout and survey were discussed for this intersection.
An improvement to this intersection was approved at the March 3, 2020 Board of Commissioners Meeting. Improvements will be covered with SPLOST funds.
Atlas Engineering was awarded the contract to design the intersection for $195,000 on March 17, 2020.
Public Works: Requested approval by BOC to purchase Right of Way and Easements for the Roundabout at Jack Neely and Kirkland. It was approved on March 2, 2021. Chester Clegg is handling this project.